AI data-center construction

Vineland shows 67,900 m² of persistent change inside the campus in August 2026.

What this tells you

  • On Sep 8, 2025, Nebius promised Microsoft capacity at Vineland. Nebius filing
  • Nebius cut its outlook on Nov 12, 2026. Nebius lowered its 2026 revenue outlook to the low end of its range after third-party data-center delays.Shareholder letter
  • 3 of 8 campuses show measurable growth. 2 conversions have work inside existing buildings.
Physical AI build pace (8 tracked campuses)

Net footprint added each month (m²). The line covers 6 campuses with visible work.

How we measure

Across the latest six complete readings, growth above the campus’s own noise floor (twice its median month-to-month swing, at least 40,000 m²) is Building. Change within that floor is Flat. Interior and brownfield work is Can't see from orbit.

Sentinel-2 records one view per month. Inside each campus boundary, we exclude cropland and count 10 m pixels that stay changed in at least 70% of later clear scenes.

September through November 2026 have too few later scenes to confirm change. The viewer shows their provisional measurements. The charts end in August.

Build pace compares consecutive months only when every measurable campus has two clear readings. Gaps mark missing comparisons. This sample measures visible construction. Powered capacity and equipment inside a shell require company records.

  • Stargate Abilene. A roof can be complete before the servers come online.
  • Hyperion. The southern end extends beyond the image.
  • Colossus 2. The Memphis image ends before the Southaven expansion.
  • Colossus 1. Factory equipment upgrades happen inside the existing shell.
  • Fairwater. The second shell is visible. Its interior equipment is below the resolution of these images.
  • Project Rainier. The scene covers the southern buildings and one northern pad.
  • Denton. The old mine buildings keep the same roofs during conversion.
  • Vineland. A larger footprint shows civil works. Turning on the chips can take longer.

Campus tracker

8 of 8 campuses
AMZNANTBECATCORZCRWVETRGEVMETAMSFTNBISNVDAORCLTSLASPCX

By company

Colossus 2 · Memphis, TN

Building

Clear readings through · Footprint +139,300 m² from Feb 2026 to Aug 2026.

Aerial photo of Colossus 2 · Memphis, TN, Aug 2023
Satellite · Nov 2026 · 10 m of Colossus 2 · Memphis, TN
Aerial · Aug 2023Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Aug 20, 2023 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

245,700 m² · Provisional

Who it hits

Read-through, not a recommendation

  • SPCX

    watch · SpaceX brings GPU clusters online in stages. Each powered hall adds capacity for its AI business. Source

  • ANT

    watch · Anthropic contracted for GPU capacity here. New halls could give Claude more room to run. Source

  • NVDA

    tailwind · SpaceX has put NVIDIA GB200 and GB300 chips into service here as it expands the cluster. Source

  • CAT

    watch · Caterpillar’s Solar Turbines units supplied power at the Southaven plant serving Colossus 2. Source

  • GEV

    watch · GE Vernova mobile turbines helped power the campus from Southaven during the buildout. Source

  • TSLA

    watch · Tesla Megapacks store power on campus. More batteries would signal another storage expansion. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

Loading closes…

What would change the read

Six or more months of flat footprint would weaken the construction signal.

Persistent footprint (m²)Monthly CSV

Construction record

The campus was running in June 2026. The third roof was about half complete.

Epoch AI

Stargate · Abilene, TX

Flat

Clear readings through · No measurable footprint change from Mar 2026 to Aug 2026; swings under 122,400 m² are seasonal noise.

Aerial photo of Stargate · Abilene, TX, Jul 2022
Satellite · Nov 2026 · 10 m of Stargate · Abilene, TX
Aerial · Jul 2022Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Jul 26, 2022 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

1,176,100 m² · Provisional

Who it hits

Read-through, not a recommendation

  • ORCL

    watch · Oracle runs the cloud capacity OpenAI uses here. Watch when new halls start serving workloads. Source

  • NVDA

    watch · Oracle delivered NVIDIA GB200 racks to Abilene. More rack deliveries would confirm demand for more chips. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

Loading closes…

What would change the read

More than 122,400 m² of growth across six clear readings, or confirmation that more capacity is online.

Persistent footprint (m²)Monthly CSV

Construction record

Oracle reported six of eight buildings delivered by September 2026. Epoch estimated the last two would open in November.

Crusoe (developer) · OpenAI (capacity customer)

Epoch AI

Microsoft Fairwater · Mount Pleasant, WI

Building

Clear readings through · Footprint +928,100 m² from Feb 2026 to Jul 2026.

Aerial photo of Microsoft Fairwater · Mount Pleasant, WI, Jun 2022
Satellite · Nov 2026 · 10 m of Microsoft Fairwater · Mount Pleasant, WI
Aerial · Jun 2022Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Jun 23, 2022 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

977,900 m² · Provisional

Who it hits

Read-through, not a recommendation

  • MSFT

    watch · Microsoft has brought the first facility online. Opening another would add capacity to its Wisconsin campus. Source

  • NVDA

    watch · Fairwater runs NVIDIA Blackwell chips. New rack installations would confirm the next stage of deployment. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

Loading closes…

What would change the read

Six or more months of flat footprint would weaken the construction signal.

Persistent footprint (m²)Monthly CSV

Construction record

Building one was running in April 2026. By May, building two had a nearly finished shell.

Epoch AICampus source

Meta Hyperion · Holly Ridge, LA

Building

Clear readings through · Footprint +1,253,100 m² from Mar 2026 to Aug 2026, the fastest growth per month among the tracked campuses.

Aerial photo of Meta Hyperion · Holly Ridge, LA, Jul 2023
Satellite · Nov 2026 · 10 m of Meta Hyperion · Holly Ridge, LA
Aerial · Jul 2023Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Jul 18, 2023 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

3,243,700 m² · Provisional

Who it hits

Read-through, not a recommendation

  • META

    watch · Hyperion will add training capacity for Meta once the new halls have power. Source

  • ETR

    tailwind · Meta agreed to cover the cost of new Entergy infrastructure to power Hyperion over 20 years. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

Loading closes…

What would change the read

Six or more months of flat footprint would weaken the construction signal.

Persistent footprint (m²)Monthly CSV

Construction record

The first two roofs were in place by April 2026. Epoch projected a first-phase opening in early 2028.

Epoch AICampus source

Project Rainier · New Carlisle, IN

Flat

Clear readings through · No measurable footprint change from Mar 2026 to Aug 2026; swings under 59,300 m² are seasonal noise.

Aerial photo of Project Rainier · New Carlisle, IN, Jun 2022
Satellite · Nov 2026 · 10 m of Project Rainier · New Carlisle, IN
Aerial · Jun 2022Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Jun 16, 2022 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

384,200 m² · Provisional

Who it hits

Read-through, not a recommendation

  • AMZN

    watch · Rainier puts Amazon’s own Trainium chips to work for AWS customer Anthropic. Source

  • ANT

    tailwind · Anthropic trains Claude on Rainier. More chips in service would expand its training capacity. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

Loading closes…

What would change the read

More than 59,300 m² of growth across six clear readings, or confirmation that more capacity is online.

Persistent footprint (m²)Monthly CSV

Construction record

The measured footprint has stayed within 59,300 m² of its March 2026 reading.

Buildings 17 and 18 had roofs by June 2026. Earlier buildings were already running.

Epoch AI

Nebius · Vineland, NJ

Flat

Clear readings through · No measurable footprint change from Mar 2026 to Aug 2026; swings under 40,000 m² are seasonal noise.

Aerial photo of Nebius · Vineland, NJ, Aug 2023
Satellite · Nov 2026 · 10 m of Nebius · Vineland, NJ
Aerial · Aug 2023Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Aug 20, 2023 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

54,600 m² · Provisional

Who it hits

Read-through, not a recommendation

  • NBIS

    risk · Delays in bringing Vineland capacity online can push back revenue under the Microsoft contract. Source

  • MSFT

    risk · A late handover would delay access to the GPU capacity Microsoft booked at Vineland. Source

  • BE

    watch · Bloom Energy fuel cells are due to power the site. Watch when the permanent power supply comes online. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

Loading closes…

What would change the read

More than 40,000 m² of growth across six clear readings, or confirmation that more capacity is online.

Persistent footprint (m²)Monthly CSV

Construction record

The measured footprint has stayed within 40,000 m² of its March 2025 reading.

Epoch estimated 50 MW in service. In July 2026, it saw more cooling equipment awaiting connection.

DataOne (developer / operator)

Epoch AICampus source

Colossus 1 · Memphis, TN

Can't see from orbit

Clear readings through · Through Aug 2026, the satellite record cannot measure progress inside the existing buildings.

Aerial photo of Colossus 1 · Memphis, TN, May 2023
Satellite · Nov 2026 · 10 m of Colossus 1 · Memphis, TN
Aerial · May 2023Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · May 3, 2023 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

21,400 m² · Provisional

Who it hits

Read-through, not a recommendation

  • SPCX

    watch · SpaceX contracted the full capacity of this converted factory to Anthropic. Source

  • ANT

    tailwind · Access to the Memphis cluster gives Anthropic more capacity to serve Claude customers. Source

  • NVDA

    watch · Anthropic’s capacity deal covers NVIDIA GPUs already installed inside the factory. Source

  • TSLA

    watch · Tesla supplied Megapacks to support the original Memphis cluster as its GPU load grew. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

What would change the read

A dated company report confirming new capacity, or a delay in bringing it online.

Persistent footprint (m²)Monthly CSV

Construction record

Anthropic agreed in May 2026 to use all compute at the converted factory.

Epoch AICampus source

CoreWeave · Denton, TX

Built before our baseline — change tracking starts from here

Clear readings through · Through Aug 2026, the satellite record cannot measure progress inside the existing buildings.

Aerial photo of CoreWeave · Denton, TX, Jul 2022
Satellite · Nov 2026 · 10 m of CoreWeave · Denton, TX
Aerial · Jul 2022Satellite · Nov 2026 · 10 m

USDA NAIP via Microsoft Planetary Computer · Jul 3, 2022 and Jul 13, 2022 · Full-size aerial

Monthly satellite · 10 m · for change, not detail

Who it hits

Read-through, not a recommendation

  • CRWV

    watch · CoreWeave has contracted for 262 MW at Denton. Watch how much capacity it can deliver to cloud customers. Source

  • CORZ

    watch · Core Scientific earns hosting fees at Denton. Power or cooling outages can trigger credits to CoreWeave. Source

Next dates

  • Sentinel-2 · Dec 2026 scene expected (monthly).

What would change the read

A dated company report confirming new capacity, or a delay in bringing it online.

Monthly CSV

Construction record

Seven converted buildings were running by July 2026. Epoch projected the eighth would open in May 2027.

Epoch AICampus source

Credits

Research, not financial advice. RADAR Hedge may hold positions in names discussed.