What the filing says

WULF

Claims

  • The Company's data center lease arrangements generally range from 10 to 25 years.
  • As of September 30, 2026, the Lake Mariner Data Campus had 102 MW of energized critical IT HPC capacity.
  • As of September 30, 2026, the Lake Mariner Data Campus had 145 MW of legacy bitcoin mining capacity.
  • During the nine months ended September 30, 2026, certain mining facilities were curtailed or repurposed to support HPC development.
  • There have been no material changes to the risk factors set forth in the Annual Report on Form 10-K for the fiscal year ended December 31, 2025, and subsequent Quarterly Reports on Form 10-Q.

Changes vs prior

  • During the nine months ended September 30, 2026, certain mining facilities were curtailed or repurposed to support HPC development, consistent with the Company’s strategic transition.
  • There have been no material changes to the risk factors set forth in the Annual Report on Form 10-K for the fiscal year ended December 31, 2025, and subsequent Quarterly Reports on Form 10-Q.