This week’s reports, read from filings and releases.
WULF 10-Q
Filed 2026-11-06 · SEC source filing (opens in a new tab)
AI-generated digest; each statement was machine-checked against the filing text and unverified ones are left out. Not a substitute for the filing. Not investment advice.
What the filing says
WULFClaims
- The Company's data center lease arrangements generally range from 10 to 25 years.
- As of September 30, 2026, the Lake Mariner Data Campus had 102 MW of energized critical IT HPC capacity.
- As of September 30, 2026, the Lake Mariner Data Campus had 145 MW of legacy bitcoin mining capacity.
- During the nine months ended September 30, 2026, certain mining facilities were curtailed or repurposed to support HPC development.
- There have been no material changes to the risk factors set forth in the Annual Report on Form 10-K for the fiscal year ended December 31, 2025, and subsequent Quarterly Reports on Form 10-Q.
Changes vs prior
- During the nine months ended September 30, 2026, certain mining facilities were curtailed or repurposed to support HPC development, consistent with the Company’s strategic transition.
- There have been no material changes to the risk factors set forth in the Annual Report on Form 10-K for the fiscal year ended December 31, 2025, and subsequent Quarterly Reports on Form 10-Q.