WULFClaims
- WULF's growth strategy depends on the timely development of its HPC data centers, including the Cayuga Site in Lansing, New York.
- In July 2026, New York Governor Kathy Hochul issued Executive Order No. 62, which temporarily pauses certain discretionary permits and approvals for covered data center projects.
- WULF does not currently expect the temporary moratorium to materially affect the development timeline for the Cayuga Site.
- The Company's data center lease arrangements generally range from 10 to 25 years.
- Certain data center lease arrangements benefit from investment-grade credit support.
Changes vs prior
- There have been no material changes to the risk factors set forth in the Annual Report on Form 10-K for the fiscal year ended December 31, 2025, except for the new risk factor regarding New York State's temporary moratorium on data center permitting.