NXE 6-K
Filed 2026-11-10 · SEC source filing (opens in a new tab)
AI-generated digest; each statement was machine-checked against the filing text and unverified ones are left out. Not a substitute for the filing. Not investment advice.
What the filing says
NXEClaims
- The filing includes unaudited condensed interim consolidated financial statements for the periods ending September 30, 2026 and 2025.
- The filing includes Management's Discussion and Analysis for the three and nine months ended September 30, 2026.
- NexGen announced results from the early portion of the 2026 summer drilling program at PCE on August 25, 2026.
- A fifth drilling rig was added to the program to further advance exploration based on the early results.
- As of September 30, 2026, 28,712 metres had been drilled.
- The Rook I FS Technical Report indicates that NPV and IRR are most sensitive to uranium price, head grade, process recovery, and exchange rates.
- The Interim Trend Update indicates that positive after-tax NPV (8%) is maintained across the range of uranium price scenarios, including at US$30/lb U₃O₈.
- Construction of the Rook I Project commenced on June 8, 2026, following receipt of the Licence on March 5th, 2026.
- The Company is progressing the Rook I Project materially on schedule, budget, and to scope.
- During the fourth quarter of 2026, the Company aims to complete the Project airstrip runway to 5,840 feet.
- Leigh Curyer, Chief Executive Officer of NexGen Energy Ltd., certified the interim financial report and interim MD&A for the period ended September 30, 2026.
- The certification was dated November 9, 2026.
- Ryan Podrasky, Chief Financial Officer of NexGen Energy Ltd., certified the interim financial report and interim MD&A for the period ended September 30, 2026.
Changes vs prior
- A fifth drilling rig was added to the program based on results from the early portion of the 2026 summer drilling program.
- NexGen Energy Ltd. disclosed in its interim MD&A any change in internal control over financial reporting that occurred during the period from July 1, 2026 to September 30, 2026, that materially affected or is reasonably likely to materially affect the issuer's ICFR.