IREN 10-Q
Filed 2026-11-05 · SEC source filing (opens in a new tab)
AI-generated digest; each statement was machine-checked against the filing text and unverified ones are left out. Not a substitute for the filing. Not investment advice.
What the filing says
IRENClaims
- Certain contracted capacity targeted for delivery by December 31, 2026 is now expected to be delivered during the following quarter due to a customer-requested design change, supply timing, and third-party delays.
- The company continued to operate Bitcoin miners at its data centers during the three months ended September 30, 2026.
- The company reported no material changes to its risk factors compared to those disclosed in its Annual Report.
Changes vs prior
- The delivery timeline for certain contracted capacity was delayed from December 31, 2026 to the following quarter.
- There were no material changes to the company's risk factors relative to the prior Annual Report.