AAOI 8-K

Filed 2026-09-01 · SEC source filing (opens in a new tab)

AI-generated digest; each statement was machine-checked against the filing text and unverified ones are left out. Not a substitute for the filing. Not investment advice.

What the filing says

AAOI

Claims

  • Applied Optoelectronics, Inc. entered into two lease agreements with Hightower Phase II Owner, LLC for two industrial buildings to be constructed in Houston, Texas.
  • The Landlord is an affiliate of Hightower Phase I Owner, LLC, which is the landlord under the Company's three previously disclosed lease agreements for Buildings 1, 2, and 3.
  • Substantial completion of the buildings is anticipated approximately 16 months following the date of the Leases.
  • Each Lease has an initial term of 120 full calendar months, plus any partial month from the commencement date to the end of the calendar month in which the commencement date occurs.
  • If work is not substantially completed by 18 months following the date of the Leases, basic rent will be abated by one day for each day thereafter until substantial completion.
  • If actual delivery has not occurred by 24 months following the date of the Leases, the Company may terminate the applicable Lease on 30 days' advance written notice.
  • The Company is responsible for 100% of operating costs, taxes, and insurance costs allocated to each building.
  • The Building 4 Lease consists of approximately 356,186 rentable square feet of industrial space.
  • The Building 5 Lease consists of approximately 737,621 rentable square feet of industrial space.